The number everybody guesses
Ask five superintendents what their crew costs per foot and you get five numbers, all from memory, none of them written down. It works until the job that looked fat comes in flat — and by then the footage is in the ground and the money is gone.
Cost per foot is not a gut feel. It is arithmetic, and it is the same arithmetic whether you are pulling fiber, laying water main, or stringing conductor. Three inputs, one division.
The math
Start with a fully-loaded weekly crew cost, then divide by the feet that crew actually puts in the ground in a week.
- Weekly labor = crew size × blended wage × hours, then × (1 + burden). Burden is not optional — payroll tax, workers comp, and benefits routinely add 30–40%.
- Weekly equipment = the trucks, machines, and fuel that sit on that crew whether it produces or not.
- Weekly cost ÷ weekly production (in feet) = your cost per foot.
The three things that wreck it
Every contractor who gets burned gets burned by one of these:
- Burden left out. Quoting off the raw wage instead of the loaded wage understates every crew by a third. It is the single most common estimating mistake in this trade.
- Idle iron ignored. A bucket truck costs the same on a slow week as a fast one. If it is assigned to the crew, it is in the cost per foot.
- Ideal production, not real. The rate the crew hits on a perfect blue-sky day is not the rate they average across weather, locates, and reel changes. Use the honest number.
Why the decimal matters
A ten-cent error in cost per foot feels like a rounding difference. On a 500,000-foot build it is fifty thousand dollars — the difference between a good year and a callback to the bank.
Get it right once, off real inputs, and every bid, every crew comparison, and every deadline decision downstream inherits a number you can trust.