Start from the date, not the crews
A hard completion date and a total footage is a solvable problem, not a coin flip. Work backwards: the schedule tells you the production you need, and the production tells you the crews.
- Required weekly production = total footage ÷ weeks available.
- Crews needed = required weekly production ÷ what one crew actually produces in a week.
- Round up. A fractional crew is a full crew, and the schedule has no slack for the remainder.
Overtime or another crew?
When the math says you are one crew short, you have two levers, and they do not cost the same.
Overtime buys production without mobilization, but it buys it at a premium and with diminishing returns — hour twelve is not as productive as hour eight, and burnout shows up as errors and turnover. A second crew adds clean production but also adds a truck, a foreman, and the management drag of one more moving part.
The trap: adding crews late
The instinct when a schedule slips is to throw crews at it. It rarely recovers the way the spreadsheet promises. New crews ramp up, the ones training them slow down, and the site gets more congested, not more productive.
The time to solve the crew count is before mobilization, from the honest per-crew rate — not in week ten from a panic.